Railway Track Bed - Swamp Grid®

Swamp Grid

Industry

Civil Infrastructure

Challenge:

A 45-mile stretch of railway track from Edmonton to Edson, Alberta was successfully twinned during winter, with materials installed on challenging muskeg, bog-like ground.

Achievement:

Using Swamp Grid™ 30 helped the client reduce costs and construction time, while Titan’s prompt material delivery enabled early project completion—allowing for track settlement ahead of schedule.

Product Used:

Swamp Grid®

Location: Wildwood, Alberta

Project Type: Product Supply - Railway Track Bed Twinning

Product Used: Swamp Grid® 30

Challenge

A 45-mile portion of railway track beds that stretch from Edmonton to Edson, Alberta was to be twinned. Not only was this project completed during the winter months, the material also needed to be installed on muskeg, bog like ground.


Titan Solution

Swamp Grid - Rail (002)

Swamp Grid® 30 was an optimal way to stabilize the railway track bed poor soil conditions. The design consisted of three lifts. Each lift included one layer of Swamp Grid™ 30 along with gravel to help improve structural stability. Titan supplied a total 134,000m2 (678 rolls) of Swamp Grid®.

Titan was responsible for building the entire dome which included assembling and utilizing an impressive 91 meter (300 ft) centrally located tower to facilitate lifting and construction in sections.

Swamp Grid® is an advanced composite geogrid product consisting of our Titan Earth Grid® heat-bonded to a long-fiber PET nonwoven geotextile.

Achievement

Using Swamp Grid® 30 saved the client money on materials, construction time and resources. Due to Titan's extensive inventory and ability to get the material shipped to site in a quick and timely manner the client was able to complete the project ahead of schedule. Early completion was an added bonus as it allowed for settlement before building the track.