Cofferdam Solution - Great Falls, MB

Cofferdam Solution

Industry

Water Management

Challenge:

The project’s main challenge was controlling river water to safely blast bedrock on the riverbank for outfall pipe installation, requiring a fast, effective temporary water barrier.

Achievement:

We offered a cost-effective solution and worked with our supplier to provide the client with installation site assistance.

Product Used:

Cofferdam

Location: Great Falls, Manitoba (Winnipeg River)

Project Type: Supply and Installation

Product Used: 13 Cofferdam Tubes

Challenge

Hold back river water during local blasting operations.


Titan Solution

Titan supplied 13 cofferdam tubes of varying lengths for a water treatment plant outfall pipe installation on the bank of the Winnipeg River. To complete the installation, the contractor needed to blast through local bedrock along the riverbank, which required holding back the surrounding river water. They turned to Titan for a solution, and we recommended cofferdams—tube-like structures made from industrial-grade PVC. Easily deployed and inflated with river water, the cofferdams quickly formed a temporary dike, effectively keeping water away from the blast zone and enabling safe, dry working conditions.

Achievement

We offered a cost-effective solution and collaborated with our supplier to provide the client with on-site installation assistance.

 